Gurney Bay project: Chow denies Phase 1 costs RM247 mil, clarifies that is total cost

Penang CM says full amount to be paid when works completed in 2026, contractor still liable for damages

7:37 PM MYT

 

GEORGE TOWN – Penang Chief Minister Chow Kon Yeow has denied allegations that Phase 1 of the Gurney Bay project cost RM247 million and stressed that the contractor is still responsible for any damage at the site. 

He said in a statement that RM247 million is the full cost of the Gurney Bay project, namely phases 1 and 2. 

“As of December 31, 2023, the state government has only paid RM58 million for the completed work. The RM247 million will only be spent when all components of the project are completed by 2026. 

“As for damage at the site, the contractor is responsible for two years under the damage liability period condition,” he said. 

Yesterday, Chow announced the opening of Phase 1 of Gurney Bay to the public and described it as a recreational park suitable for the whole family, with it uniquely located by the seaside. 

Former chief minister Lim Guan Eng had earlier uploaded a post on Facebook questioning the quality of work at the recently-opened recreational park, which is already showing defects. 

“The RM247 million spent should bring an international-standard recreational park,” said Lim, who is also the Air Putih assemblyman. – February 5, 2024

Topics

 

◉ Popular

No, Malays could not fly: Scholars call out pseudohistory

UPSI and DBP academics urge discipline in handling history after Prof Solehah’s claims of Malays teaching China ‘flying kung fu’

38% of AirAsia flights delayed in 2024: Loke

Minister outlines measures to improve on-time performance, including incentives, penalties, and full refunds for major delays

Penjawat awam kerja dari rumah tiga kali seminggu, syarat daftar SPOT-Me setiap sejam

Tempat bekerja pegawai semasa BDR ialah di rumah yang didaftarkan dalam Sistem Pengurusan Maklumat Sumber Manusia (HRMIS) sahaja

◉ Related