Pan Borneo Highway: land acquisition issues among reasons for delay in Sabah, says Nanta

Works minister says other challenges faced include changes to contract, need for capacity enhancements, Covid-19, others

9:57 PM MYT

 

KUALA LUMPUR – Land acquisition delays and changes in project implementation methods have led to slower progress in the construction of the Pan Borneo Highway in Sabah compared to Sarawak. 

Works Minister Datuk Seri Alexander Nanta Linggi said besides changes to contracts, the need for capacity enhancements and existing technical expertise are among the challenges faced in the project’s implementation in Sabah. 

“Unlike the project in Sarawak which commenced in 2015, the project in Sabah began in 2016. 

“Furthermore, only a portion of the 35 work packages continued construction, while the remaining work packages, particularly Phase 1B, had to be relooked into due to changes in implementation methods and are expected to commence only this year. 

“At the same time, just like other government projects, the Covid-19 pandemic has impacted the progress and construction costs of the Pan Borneo Highway project in Sabah. 

“However, the government remains committed to ensuring the smoothness and sustainability of the project,” he said. 

He said this during a special chamber session in the Dewan Rakyat today in response to issues raised by Isnaraissah Munirah Majilis (Kota Belud-Warisan) regarding the slower progress of the Pan Borneo Highway project in Sabah compared to Sarawak. 

As a measure for improvement, Nanta said a Project Management Consultant (PMC) has been appointed to assist the Sabah Public Works Department (JKR) in expediting the project through various mitigation plans, including rescheduling construction schedules and providing Extensions of Time (EOT) to contractors. 

“For the remaining 19 Work Packages of the Pan Borneo Highway project Phase 1B in Sabah, the government is currently finalising the procurement process and this is expected to be finalised in the second quarter of 2024, completing the entire stretch of the Pan Borneo Highway project Phase 1 in Sabah,” he said. – March 21, 2024

Topics

 

◉ Popular

Subsidised RON95: how cheap is Malaysia’s fuel compared to neighbours?

There has been a spate of viral videos showing vehicles from neighbouring countries such as Thailand and Singapore being filled with Malaysia's heavily subsidised RON95 petrol, indicating a blatant disregard for local laws.

MACC probes IJM over alleged RM2.5bil money laundering scheme, Sunway takeover at risk

The Malaysian Anti-Corruption Commission is probing IJM Corporation over alleged money laundering and possible share price manipulation involving RM2.5bil, a probe that could jeopardise Sunway Group’s proposed RM11.5bil takeover of the construction giant

Jakim, Islamic affairs get RM2 bil under Budget 2025

This includes maintenance for educational infrastructure under dept, increased Kafa teacher quota, rehabilitation for GISB kids

◉ Related